Porch renovation - Week 5 (Jun 25-Jul 7)
Work centered on finishing the column bases, installing the columns, trimming out the columns and base and finally installing a ceiling. Work remaining at this point includes instlaling the railings between columns, siding the skirt around the porch base, recasing the east and north east windows and the front door and residing the north/front of the house.
We've also decided to upgrade the lighting package a bit. In addition to the two overhead fixtures and the entry way coach light, we've decided to put small low-volt halogens at the top of each column washing down. This came around as we were deciding how and where to mount the house number plaque and how folks would see it at night. When we tried it out wuth a flash light, it looked great. So I ran low-volt wiring in the ceiling (just before the sealed it up) and ordered the low volt fixtures.
Last updated July 9, 2001